ANAHEIM STREET PUMP STATION, situated in Long Beach at the
Dominguez Channel, was a challenge. With a 43 foot deep pit, there were
going to be 12 big struts intersecting the pump station walls at 24
locations. That's 48 intersections through each form. Yeager/
Skanska hired August Construction to solve this challenge, and we did - by
designing an elliptical pit. Not only were the struts eliminated,
but there was more room to work to speed the construction of the pump
station. A good example of August Construction's "value
engineering". |