|
MICROPILES
SECURE NORTON AIR
FORCE BASE COMPLEXES
|
Norton Air
Force Base required, like so many public buildings in
California, to upgrade for earthquake compliance. This was
accomplished by installing multiple shear walls with an independent
foundation from the existing spread footing columns which supported the
two story concrete waffle floor type of buildings.
The
project design engineer was Sverdrup, which specified MICROPILES for the
foundation support for the shear walls. Groupings of two and three
micropiles was used on each end of the 20 long pile caps. These
micro piles extended 50 feet below the existing grade. RQ
Construction, which specializes in government facilities, selected August
Construction for the installation of the micro piles. August
Construction used a Davey Kent 525 rotary percussion rig to access under
the 17 foot headroom 
|
Drill mast under waffle
ceiling at one of two Norton Air Force Base buildings being
renovated and upgraded to current Earthquake codes . Here, one
of five shear walls will be constructed between columns and
secured by 4 to 6 ultra-high capacity micropiles.
|
|
|
Three
completed
50 foot deep ultra-high capacity micropiles protrude 4.5 feet into the pile cap
area to support one end of a shear wall footing.
|
(after pile cap excavation) in order to drill the 10
inch nominal diameter micropiles using a Titan 103 rod (hollow tendon
which is used to drill while grouting to flush the cuttings, and then left
in the hole to act as the reinforcing steel). The drilling was very difficult in
the rocky and caving soil, but far easier than if a conventional pile had
been designed (2-3 foot typically). The obvious advantage of the
micropile design was the use of a small diameter and a single rod
design. Additionally, with the use of the Titan hollow bar, there
was no need to case the caving soils because the grout acted as the
flushing medium to keep the hole open, while conditioning the hole. The
Titan rod was coupled in 10 foot sections and had a plate with
a nut on top and bottom of the plate. The rod was bonded to the soil
using Neat cement (water and cement without aggregate).
The testing program required 2 micropiles in compression and 2 in
tension. The bearing length of the micro piles was from 18 to 23 feet
in a sandy, gravel and cobble matrix about 25 feet below grade
level. That proved to be an exceptionally good soil for
bonding, and the piles easily achieved 400 kips (kip = 1,000 lb) in
tension and compression. The top of the micropiles was designed with
a 20 foot steel structural pipe collar (8" diameter).
|
|