|
Micropiles Secure Robinson May Department
Store
One of the greatest challenges to Owners and Contractors in the renovation of existing
buildings, is the need to keep the facility operational during the
construction period. Keeping a site open was the challenge facing
Robinson-May Department store in Laurel Plaza during a recent seismic
upgrade. The original plan required forty-four 24"diameter piles up
to 50' deep inside the basement level of the store at eleven column locations. To
install, extensive demolition was required; the removal of the main
electric panels and portions of the internal stairwells. That was an undesirable prospect for the
owners, who had as a minimum requirement an
open store during the construction.

| Micropile drill rig being pushed
through the showroom lingerie department for drilling location at
column footing. |
It was clear that an alternate plan had to be conceived and
implemented. Just days before bid date, the owner suggested they would be
open to micropiles (even though the engineered plan was complete and
submitted for a permit). To address the owners needs for a practical
construction solution, Bob Morrison of Morley Construction worked closely
with August Construction, a specialty drilling contractor, to substitute
large diameter piles, (24" plus) with Micropiles (7" in
diameter) to clinch the winning bid.
August Construction called upon the services of Ulf Werner &
Associates to modify the existing plan and Groundtech to provide
construction and testing procedures. The new design employed two to six
Micropiles per column to reflect the actual forces required. In order to
determine the length / capacity of the Micropiles, August worked with
Law/Crandall, the soils engineers. Three Micropiles were installed in the
parking lot prior to final design. When tested, the 7" diameter
Micropiles (1 3/8" diameter, Grade 150ksi from Williams
Form Engineering) were
"post-grouted" with neat cement and produced greater capacity
than that assigned to the 24" diameter piles. Because the greatest
loads required were all in tension (not compression). The Micropiles were
tested in tension as follows: Group action of 2 @ 25 foot micro piles (tiedowns)
at 504 kips. Test of 1 @ 35 foot micro pile (tiedown) at 320 kips and 1 @
25 foot micro pile (tiedown) at 324 kips. None of the micro piles failed.
However after careful analysis, a design load of 7.6 kips/ foot was chosen
by the engineers for the final design values. |

|
Drilling at the pile cap columns with
micro pile drill rig. |
The primary advantage of Micro or mini piles in this application was that the
holes could be drilled inside an "active store" site. Due to
the size and mobility of Augusts drill rigs, the rigs could be
maneuvered inside the store to drill the holes without extensive
demolition (as would have been required with traditional piles). Some of
Augusts custom drill units successfully drilled 50 foot holes (in sandy
matrix and river bed boulders) and yet were small enough to be able to fit
between steel column and concrete walls a mere 2 foot distance. This
type of equipment adaptability saved the power panels and stairwells a
major economic savings. Additionally, Augusts equipment was remotely
powered (in the parking lot) which totally eliminated the noise and
pollution from the engine, a key benefit when working inside an active
store.

|
Accessing through hall with micropile
drill rig from loading ramp. |
"If the owners construction department had not expressed an
openness to an alternate design just a few days before bid-date, the
original design would have been implemented to disastrous effects Im
sure", Agust Agustsson, the project manager for August Construction
noted. "Its really to their credit that they recognized that a
more elegant solution could be implemented; and the plan was modified and
refined and approved without delaying the project."

| Micropile, consisting of #11 high
strength all-thread bar from Williams Form Engineer is just visible
between the column brackets and is surrounded by the numerous dowels
embedded in the original spread footing. . |
|