FORT MacArthur slope repair

View of Fort MacArthur during final slope repair Phase

Tensar geogrid utilized to add extra strength to slopes Installation of the Mecanically Stabilized Earth (MSE)

Fort MacArthur situated in San Pedro atop 40 foot bluffs, suffered a slope failures.  Earth Tech designed and managed the project and August Construction repaired the slope. In order to minimize the loss of usable property at the top of slope, a combination of Mecanically Stabilized Earth and compaction with Tensal geogrid was utilized.  The unstable portion that had only raveled received a 2:1 slope trimming. 

Typical slope application of MSE wall at 1:8 slope face